Exercise 1 of 6
In project estimation & delivery, which lens does this check belong to: “What happened on the most comparable completed work, and why should this case be faster or slower?”
Show the best first lens
Planning Fallacy
What happened on the most comparable completed work, and why should this case be faster or slower?
Evidence note The planning fallacy is a well-documented tendency for people to predict their own task completion times too optimistically. The effect has been observed across different kinds of tasks, but it is not a rule that every plan will run late. Project overruns can also come from changing scope, dependencies, incentives, poor data, deliberate underestimation, or genuinely unusual events, so a late project should not automatically be diagnosed as a planning fallacy.